Doubling and electrifying the Mahbubnagar Dhone railway line will boost connectivity between Secunderabad and Guntakal.
TelanganaRight to Information (RTI) reply on section wise tendering dates and planned completion dates of Mahbubnagar Dhone railway doubling.
Mahbubnagar Dhone railway double line section wise tendering dates and planned completion dates.
Targetted Section | Tender Info | Tentative Date | |
---|---|---|---|
Mahbubnagar - Manyamkonda | Tender awarded on 24.07.2024 | Tentative date of completion for this section is 2026-27 | |
Manyamkonda - Perur | Tender invitation is under process | Tentative date of completion for this section is 2027-28 | |
Perur - Gadwal | Tender invitation is under process | Tentative date of completion for this section is 2028-29 | |
Gadwal - Allampur | Tender invitation is under process | Tentative date of completion for this section is 2028-29 | |
Allampur - Ulindakonda | Tender invitation is under process | Tentative date of completion for this section is 2028-29 | |
Ulindakonda - Dhone | Tender invited, agency to be fixed. | Tentative date of completion for this section is 2026-27 | |
Note: All targets are tentative subject to timely handing over land by State Govt. |